Nuclear energy
Hold points and commissioning windows built into the schedule, with risk analysis for inspection and licensing uncertainty.

Supporting service
The Primavera P6 schedule is developed from the first baseline and maintained through regular progress updates. Contractor schedules are combined into one coordinated schedule, and the dependencies between design, procurement, installation and testing are checked.
At each update, we check whether a delay affects handover or can be absorbed within the schedule. If recovery is needed, you can compare the effect of each option on dates, resources and cost before choosing a sequence. You can order this service on its own or as the planning basis for construction data integration.
Contractor schedules combined, with the dependencies between design, procurement, installation and testing checked.
Access, installation order and handovers between trades checked in 4D before work starts.
Milestones and budgets tested with QSRA and QCRA, and the main risks named.
Schedule, 4D model and cost share one structure and are updated each reporting period.
Enncon establishes the P6 baseline, then updates the current schedule and reviews the critical path at each update.
Contractor schedules combined into one schedule on one WBS, with the dependencies between them checked.
Schedule activities linked to the BIM models to test access, installation order and handovers between trades before work starts.
If the project falls behind, Enncon prepares recovery schedules for contractual approval. Each option shows the impact on milestones, resources and cost.
The WBS mapped to the CBS, so planned value, earned value and actual cost are compared for the same scope and reporting date.
QSRA and QCRA estimate the likelihood of achieving a milestone or a budget and identify the main risks.
Deliverables: baseline and updated P6 schedules, 4D sequence checks, recovery schedules, earned value reports and, where required, QSRA and QCRA reports.
P6 planning and 4D · period report
Main works, week 32
| Activity | Baseline | Forecast | Critical | Float | Complete |
|---|---|---|---|---|---|
| Substructure | 0 to 4 | 0 to 4 | No | Complete | 100% |
| Superstructure | 2 to 7 | 2 to 8 | Yes | 0 wk | 90% |
| Envelope | 5 to 10 | 6 to 11 | No | 3 wk | 35% |
| MEP rough-in | 6 to 10 | 6.5 to 11.5 | Yes | 0 wk | 30% |
| Hook-up and testing | 9 to 12 | 10.5 to 13 | Yes | 0 wk | 0% |
| Commissioning | 11 to 13 | 12 to 14 | Yes | 0 wk | 0% |
| Handover | 13 to 13 | 14 to 14 | Yes | 0 wk | 0% |
Largest overrun: MEP installation, €1.4m over budget (9.5%). Committed cost includes actual cost incurred; forecasts are re-estimated by package.
| Month | Planned value | Earned value | Actual cost |
|---|---|---|---|
| M1 | 1.2 | 1.1 | 1.2 |
| M2 | 3.0 | 2.8 | 3.0 |
| M3 | 5.6 | 5.1 | 5.5 |
| M4 | 9.0 | 8.2 | 8.7 |
| M5 | 13.2 | 12.0 | 12.7 |
| M6 | 18.0 | 16.3 | 17.2 |
| M7 | 22.9 | 20.8 | 21.9 |
| M8 | 27.6 | 25.3 | 26.6 |
| M9 | 32.0 | - | - |
| M10 | 36.2 | - | - |
| M11 | 40.0 | - | - |
| M12 | 43.2 | - | - |
| M13 | 46.0 | - | - |
| M14 | 46.0 | - | - |
Earned value uses the approved baseline and the agreed progress measurement rules. The estimate at completion is re-forecast package by package with approved changes included; it is not derived from CPI alone.
Completion week, 2,000 illustrative outcomes
| Week | Outcomes | Finished by this week |
|---|---|---|
| W55 | 10 | 0.5% |
| W56 | 30 | 2% |
| W57 | 70 | 5.5% |
| W58 | 140 | 12.5% |
| W59 | 230 | 24% |
| W60 | 300 | 39% |
| W61 | 320 | 55% |
| W62 | 290 | 69.5% |
| W63 | 220 | 80.5% |
| W64 | 160 | 88.5% |
| W65 | 100 | 93.5% |
| W66 | 60 | 96.5% |
| W67 | 30 | 98% |
| W68 | 20 | 99% |
| W69 | 13 | 99.65% |
| W70 | 7 | 100% |
Risks to investigate
This example uses 2,000 synthetic outcomes. P80 is the first week by which at least 80% of those outcomes have finished. Weeks are counted from project start. The deterministic handover is week 60, shown as month 14 in the schedule.
The tools are the same on every project. What the schedule and the cost structure have to capture depends on the sector.
Hold points and commissioning windows built into the schedule, with risk analysis for inspection and licensing uncertainty.
Base build, hook-up and tool move-in on one schedule, with 4D checks of areas, routes and simultaneous operations.
Repeatable hall-by-hall schedules, long-lead equipment tied to its activities, and cost forecasts per hall.
Schedule and cost structure aligned with the bill of quantities, so measured quantities drive progress and payments.
WBS, CBS and activity coding agreed with the project, so schedule and cost share one structure from the start.
Schedule built or reviewed, contractor schedules integrated, the sequence checked in 4D and the baseline approved.
Progress measured, schedule and cost updated, and earned value and forecasts reported each period.
QSRA and QCRA where forecasts must be defended, and recovery sequences when the project falls behind.
Yes. Schedules are built and maintained in the client’s P6 database, or delivered as P6 files to the client’s standards and coding. Contractor schedules prepared in other tools can be integrated into the project schedule.
Relevant activities are linked to model objects or work zones at the agreed level of detail, and model gaps and mapping coverage are recorded. 4D supports sequence and interface reviews before work reaches site; it does not replace design checks, method statements or the authorised site team’s decisions. Where the model is suitable, extracted quantities support the forecast after reconciliation to the agreed measurement rules; non-modelled work and indirect costs are included separately.
When a date or a budget has to be defended, or when the team needs to know which risks drive the result. The analysis is only as reliable as the schedule logic and the risk register behind it, so both are checked before any simulation is run.
Yes. It can be ordered for a defined deliverable, such as a baseline, a recovery plan or a risk analysis, or as monthly support in which Enncon runs planning and cost control inside the project team.
Tell us what you are building and where you need support.