Discuss a project
A power plant under construction, with several crawler cranes working around the main building

Service 03

Project planning and cost control

Schedules and forecasts that can be defended.

Many schedules are built for submission rather than for running the work. Cost is reported separately from progress, forecasts are single dates without a confidence attached, and the sequence on paper is not the sequence the site can deliver.

This service develops and maintains the schedule, the cost control and the risk analysis on one structure. The work is done inside the client’s process, so the numbers they produce are the numbers the project runs on.

A schedule that can be built

Logic, sequence and resources checked against the model and the site, not only against the contract dates.

Cost and progress on one structure

Progress, cost and earned value measured together, so forecasts rest on verified progress.

Forecasts with a stated confidence

Dates and budgets given with their probability, and the risks that drive them named.

What the service covers

Schedule, cost and risk are built on one agreed structure and updated each reporting period, so each report states its data date and reads from the same data.

Planning and scheduling

Primavera P6 schedules and baselines developed and maintained, contractor schedules integrated and coded to one WBS.

4D sequencing

Construction sequences checked against the BIM models for access, logistics and overlapping work before they reach site.

Cost control and earned value

Cost structure set on the same WBS and CBS, so progress, cost and earned value are measured together.

Schedule and cost risk analysis

QSRA and QCRA with Monte Carlo simulation, showing how likely the planned dates and budget are and which risks drive them.

Recovery plans

Alternative sequences prepared when the project falls behind, within the contractual approval procedures.

Deliverables: schedules and baselines, 4D sequence checks, recovery plans, cost and earned value reports, forecasts to completion and, where required, QSRA and QCRA reports.

Planning and cost control · period report

Main works, week 32

Illustrative example
Baseline finishM13
Forecast finishM14
Variance4 wk late
Critical activities5 of 7
Schedule summary: baseline and forecast for seven activities, illustrative dataM1M3M5M7M9M11M13SubstructureSuperstructureEnvelopeMEP rough-inHook-up and testingCommissioningHandoverData date
Schedule summary, months from project start, illustrative data
ActivityBaselineForecastCriticalFloatComplete
Substructure0 to 40 to 4NoComplete100%
Superstructure2 to 72 to 8Yes0 wk90%
Envelope5 to 106 to 11No3 wk35%
MEP rough-in6 to 106.5 to 11.5Yes0 wk30%
Hook-up and testing9 to 1210.5 to 13Yes0 wk0%
Commissioning11 to 1312 to 14Yes0 wk0%
Handover13 to 1314 to 14Yes0 wk0%
Illustrative data, not from a client project. Reports are produced each period from the project’s own schedule and cost data.

What the schedule must capture, by sector

The tools are the same on every project. What the schedule and the cost structure have to capture depends on the sector.

Nuclear energy

Hold points and commissioning windows built into the schedule, with risk analysis for inspection and licensing uncertainty.

Semiconductors

Base build, hook-up and tool move-in on one schedule, with 4D checks of areas, routes and simultaneous operations.

Data centres

Repeatable hall-by-hall schedules, long-lead equipment tied to its activities, and cost forecasts per hall.

Civil and infrastructure

Schedule and cost structure aligned with the bill of quantities, so measured quantities drive progress and payments.

How the work runs

  1. 01

    Structure

    WBS, CBS and activity coding agreed with the project, so schedule and cost share one structure from the start.

  2. 02

    Baseline

    Schedule built or reviewed, contractor schedules integrated, the sequence checked in 4D and the baseline approved.

  3. 03

    Control cycle

    Progress measured, schedule and cost updated, and earned value and forecasts reported each period.

  4. 04

    Risk and recovery

    QSRA and QCRA where forecasts must be defended, and recovery sequences when the project falls behind.

Questions about planning and cost control

Do you work in our Primavera P6 environment?

Yes. Schedules are built and maintained in the client’s P6 database, or delivered as P6 files to the client’s standards and coding. Contractor schedules prepared in other tools can be integrated into the project schedule.

What does 4D add to a schedule?

Relevant activities are linked to model objects or work zones at the agreed level of detail, and model gaps and mapping coverage are recorded. 4D supports sequence and interface reviews before work reaches site; it does not replace design checks, method statements or the authorised site team’s decisions. Where the model is suitable, extracted quantities support the forecast after reconciliation to the agreed measurement rules; non-modelled work and indirect costs are included separately.

When is a QSRA or QCRA worth doing?

When a date or a budget has to be defended, or when the team needs to know which risks drive the result. The analysis is only as reliable as the schedule logic and the risk register behind it, so both are checked before any simulation is run.

Can the service run as monthly support?

Yes. It can be ordered for a defined deliverable, such as a baseline, a recovery plan or a risk analysis, or as monthly support in which Enncon runs planning and cost control inside the project team.

Discuss your project

Tell us what you are building and where you need support.

Get in touch